CLIENT | Project T&T |
PARTNERS | |
LOCATION | Site de Tour & Taxis I 1000 Brussels |
AREAS | 2.800 m² |
BUDGET | 4.500.000 € HTVA |
TIMING | 2013-2019 |
STATUS | Completed |
CREDIT | Georges De Kinder |
SECTOR | |
VALUES |
As part of the adaptive reuse of the Gare Maritime on the “Tour & Taxis” site in Brussels, Altiplan has been in charge of the complete restoration and adaptation of the original administrative building.
It is today a multiple use facility hosting flexible spaces dedicated to exhibitions, receptions, training…
The project has been carried out as if it was a listed building. A careful attention was given to the preservation of the morphology of the original building as well as restoring the multiple architectural details dating from the construction of the building in early XXth century.